Fishers Construction September 4, 2023
The following is an update provided by the City for Fishers construction updates this week. For the most up-to-date list, go to the Fishers Construction update page.
ROAD NOTICE UPDATES FOR THE WEEK OF SEPTEMBER 4
Here are some important updates regarding road closures and construction projects in Fishers.
- This list includes various closures in Fishers, but it does not cover all DPW projects throughout the city.
- All construction activities are subject to weather conditions and could change.
- Please plan for extra travel time in construction zones and drive distraction-free.
- More details about the Hands-Free Indiana law, effective since July 1, 2020, can be found here.
- We appreciate motorists’ patience and caution while driving through construction sites.
STATE ROAD 37 IMPROVEMENT PROJECT
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
STATE ROAD 37 AND 141ST STREET
The pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. This is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Spring of 2024. View detour routes here.
To navigate the merge, remember:
- Use the accel lane to gain speed, not stop
- Use your mirrors and pay attention
- Look for a gap in SR 37 traffic and safely merge
CLEAR PATH IMPROVEMENT PROJECT
For more information about the Clear Path Improvement Project and to sign up for text and email updates, visit clearpath465.com.
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.
The ramp from I-69 North to 82nd Street and the ramp from 82nd Street to I-69 North is currently closed through late 2023. For detour routes and additional project information, visit clearpath465.com.
NICKEL PLATE TRAIL
The City of Fishers has completed the Fishers portion of the Nickel Plate Trail between Hague Road and 106th Street. Coordination and planning are underway with Indianapolis for the final phase between Hague Road and the crossing of 96th Street.
To learn more about the Nickel Plate Trail, view the Capital Project Dashboard here.
PROJECTS NORTH OF 116TH STREET
CUMBERLAND ROAD
There are daily lane closures currently on Cumberland Road, just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.
146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT
Phase 2A traffic restrictions are in effect. These restrictions eliminate left turn movements from 146th Street onto Allisonville Road and reopen to two through lanes on eastbound and westbound 146th Street.
Utility relocation work is ongoing. Periodic lane closures may be necessary to complete this work. Please watch for flaggers and workers in and around the construction zone. Construction crews are continuing to work on storm sewer installation and roadway grading. Crews have begun working on the widening of the westbound bridge over the White River. The contractor has installed cofferdams and delineating buoys in the White River for pier construction. Please use caution if canoeing or tubing through the work zone. For additional project information, visit the 146th St. & Allisonville Rd. Project Page here.
PROJECTS SOUTH OF 116TH STREET
106TH STREET & ALLISONVILLE ROAD
There is a sanitary sewer project currently taking place at Metro Airport at 106th Street & Allisonville Road. There may be times when lane restrictions are in place on Allisonville Road. Please exercise caution in this area.
106TH STREET & HOOSIER ROAD
The intersection of 106th Street and Hoosier Road is closed for the next 60 days for the construction of a roundabout. Access into and out of the Windermere subdivision will be on Geist Road via Governors Lane. Detour route can be found here. For additional project information, view the Capital Project Dashboard here.
GEIST GREENWAY
Geist Greenway is open between Valley Crossing to 126th Street! Work will resume on the trail south of Valley Crossing Drive on or after September 1st and will remain closed until construction is finished. Construction continues to take place along Florida Road between Bowline Drive and 104th Street. For general project information, please visit Geist Greenway.
106TH STREET TRAIL RESTRICTIONS
The multipurpose trail on 106th Street from Allisonville Road to Hague Road will be restricted with temporary closures from August 22nd to September 7th for maintenance.
2023 RESURFACING PROJECT
ADA ramp and curb reconstruction has been completed in the Parks (Harvard, Oxford and Princeton Park) as part of the 2023 Resurfacing Project. These areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. Road resurfacing has begun in The Parks and Bristols. For additional project information and to view detailed exhibits, view the Capital Project Dashboard here.
GEIST HALF MARATHON & 5K
The Geist Half Marathon & 5K is just around the corner on Saturday, September 16! Road closures and restrictions will be in effect around Geist Reservoir beginning at 4 a.m. on September 16 and will continue throughout the morning. For a full list of restrictions, visit GeistHalf.com. Please note that the following closures and restrictions are subject to change as we near race day. Course marshals will do their best to allow vehicles through when there is a break in runners. However, these breaks cannot be guaranteed so we encourage you to seek an alternate route.
For more information, please visit Fishers.in.us/DriveFishers, call at 317-595-3160, or follow @DriveFishers on Twitter.